Show Homes
Interior Finish 14th Feb 2012
Lock Up - Pastering 20th Dec 2011
Lock Up - Interior Rough out 11th Dec 2011
The Bricks 7th Dec 2011
Frame Build 24-27th Nov 2011
Roof 2nd Dec 2011
Frame Complete 28th Nov 2011
The Land 30th Oct 2011
Slab 21st Nov 2011
Slab Preparation 20th Nov 2011
Pipework 12th Nov 2011
Preparation 5th Nov 2011